External works make good progress

In St Ann’s on the Stonebridge Park Estate this slide show begins with the front row of houses in Flewitt Gardens, then Dennett Close & Lytton Close. Eastham Close footpath improvements taking shape, Eastham Close & lastly Lytton Close [Green].

These photographs were taken this afternoon, and show that WATES workers are making good progress.

The area of Lytton Close [Green] and Eastham Close is nearing completion with all of the off road parking areas & paths in place, while the perimeter iron railings are almost all in place. Workers were today laying turf in the front gardens of the homes to make them look pleasing to the eye.

Work has also begun installing the 2 meter high lockable gates in the Eastham Close footpath, and reconstructing the brick wall at the side of 10 Eastham Close which will eventually be topped with an iron fence.