The local tenants & residents Association are urgently seeking new committee members to help organise public meetings, the distribution of leaflets & Newsletters and social events. You may give as little or as much of your time as you wish. If you are interested, please contact Mr Richard Pearson Tel 0115 854 3911, or Email Stonebridgetra@gamail.com
This is the latest video around the estate taken on a nice warm afternoon. [Day 15] of WATES external cladding works and still only 5 homes has been completed and no coloured rendering has been applied so far. There remains 141 days until New Year’s Eve when the cladding is meant to be finished.
The scaffolding around homes in preparation for external wall cladding, and homes nearing completion, are shown mainly in Melville gardens in the north of the estate, and later in the video in Stonebridge Road in the south-west of the Stonebridge Park Estate.
Half the homes in the bottom row of new houses in Dennet Close are now occupied, while work putting traffic calming measures on Dennet Road continues.
Beacon Hill House, the block of apartments in the middle of the western edge of the estate is nearing completion while work continues on the car parking areas at the rear of the building, and the frontages.
Magson Close is a similar story, the blocks of flats and apartments are almost complete, and the open plan frontage is being laid.
The new footpaths and road surfaces still need to be laid and new street lighting introduced all along the new Dennet Road.
I have been advised that the completion date, already extended until the end of this month, has again been extended into September.