Keepmoat Homes Ltd moved on to the site 8 weeks ago, so work is progressing well on the Stonebridge Park Estate.
Phase 8 along St Matthias Road has been half cleared and turned into an employee surface car park, with work continuing on site. Phase 1 construction work is a priority and advancing well with the foundations going in. Iron piles are being driven into the ground on Phase 2/3 to provide a stable base ready for construction work on the new homes. Phase 4 & 5 is in the process of ground clearance & preparation work.