Phase 4 (Asra)
- · Asra have planning permission to build 15 family houses for affordable rent
- · Works have been delayed due to awaiting decision from the Department of Transport on the stopping up of Limmen Gardens.
- · Lovell's anticipate start on site in November 2013 and expect to be complete by Aug 2014.
- · NCH will be undertaking plot improvement works to the existing homes immediately surrounding the new build (funding has been approved), residents will be consulted about this nearer the time.
Letters have been sent to residents living close to all these phases providing an update.