Pages

Wednesday 31 July 2013

Stonebridge Park Regeneration Update – July 2013

compound location and Phasing of works

Phase 3 & 6 (Keepmoat)

  • Keepmoat have planning permission to build 103 new family houses for market sale (27 x 2 bed & 76 x 3 bed)
  • An additional 8 will be affordable homes (4 x 2 bed & 4 x 3 bed)
  • Works are expected to be complete by Dec 2015.
  • Some activity already being seen as Keepmoat’s ground work contractor (M Lambe Construction) are undertaking tree protection work etc.
  • Attached plan shows how the building works will be phased across the site

The first phase will be the show homes which face onto St Matthias road.

  • Keepmoat’s site compound will be set up early August and will be located in the area shown as Phase 10 on the plan.
  • NCC funding will be sought to carry out boundary improvement works to the existing properties affected by the new build.

By Debra Ross (Regeneration Officer) Nottingham City Council.

No comments:

Post a Comment